The Wortley Arms Hotel
The Wortley Arms dates back to the 1750s, so we anticipated potential challenges with the existing flooring. Upon removing the old flooring, we discovered a compromised asphalt floor screed that was ineffective in preventing rising damp. Following consultations, we removed the screed, which was approximately 35mm thick, to address the underlying issues.
The original York stone slabs were revealed during the process.
Due to time constraints, we were unable to install a new floor slab. Therefore, we implemented a system that we were confident would resolve the issues and maintain the project schedule. After the slab was prepared, a resin primer was applied and sand blinded to create a key. Ardex Na screed was then mixed with aggregate to bulk the product. Once dried, Ardex DPM 1CR, an epoxy DPM, was used to control the rising moisture. After curing for 5 hours, a further coat of Ardex NA screed was applied to raise the level and ensure the floor was ready for the flooring.
Polyflor Apex 55 3mm thick was specified for optimum slip resistance and wear for a busy commercial kitchen. Perimeter walls were prepared so the vinyl floor could be coved and welded to prevent ingress of liquids and grease.
The end result is a great finish to a hard job, especially with the preparation areas not seen.
Products used:
Ardex RE5 epoxy resin
Ardex A46
Ardex NA
Ardex aggregates
Ardex dpm 1CR.
Ardex AF148 adhesives
Polyflor Apex 55 3mm